Surface dressing programme to target Selby roads in need of refresh

Several Selby area routes up for surface refresh this Spring.

Surface dressing programme to target Selby roads in need of refresh
Library Picture / Michael Trolove / Geograph / Creative Commons

Council highways teams are poised to begin a programme of road surface dressing work from the end of this week.

Each year, the North Yorkshire County Council refreshes stretches of the county’s 9,000km of roads via its surface dressing scheme. These are all done over the Spring and Summer months, between April and October.

The council says that its surface dressing solution offers a quick, efficient and cost-effective way to maintaining skid-resistant and waterproof road surfaces and helps to prevent deterioration of our roads.

It involves spraying bitumen onto the road surface then covering it with a layer of chippings. The process costs less than a fifth of the price of full resurfacing work, but can extend the life of a road by up to ten years.

Brayton Lane will be first up for a refresh in this year's programme. Work here starts this coming Saturday before and will later move to a further 17 roads during April and May.

Barrie Mason, Assistant Director for Highways and Transportation, said: ““We know the process is not popular with some drivers, mainly because of loose chippings, but the speed of the operation and its long-term benefits, as well as the short time for which motorists are inconvenienced, are important factors.

“It is important that traffic is allowed onto the new surface because chippings need traffic to fully push them into the road. However, it is also important that drivers keep to the speed limit to allow the surface to stabilise and to avoid damage to their vehicles. That is why we put in place a 20mph speed limit during the early life of the dressing.”

After dressing, the new surface is left for seven days to allow the chippings to embed then any residual chippings can be swept up before road markings are repainted.

Information boards will be erected in the areas where work is to take place and letters will be delivered to affected properties. The work will be subject to weather conditions.

 

Location Town Road no. Duration Start date Finish date
Brayton Lane Brayton C322 1.5 days 08/04/17 09/04/17
Leeds Road Selby A1238 0.5 days 09/04/17 09/04/17
Drax Airmyn link road, Padcoat Camblesforth A645 3 days 10/04/17 12/04/17
Hillam Lane Hillam C323 3.5 days 13/04/17 20/04/17
Naburn to Stillingfleet Stillingfleet B1222 1 day 20/04/17 21/04/17
Cawood Road Stillingfleet C207 1.5 days 21/04/17 22/04/17
Wheldrake Lane Escrick C303 1 day 23/04/17 23/04/17
Skipwith to Thorganby Thorganby C303 3 days 24/04/17 26/04/17
South Duffield Road Osgodby C318 1 day 27/04/17 27/04/17
Drax Airmyn link road Camblesforth A645 2 days 28/04/17 02/05/17
Cobcroft Lane, Cridling Stubbs C335 1 day 03/05/17 03/05/17
Birkin Lane Birkin C329 1 day 04/05/17 04/05/17
Cawood 2016 sites Cawood   0.5 days 05/05/17 05/05/17
Moor Lane, Ryther Ryther U782 1 day 05/05/17 06/05/17
Wighill Lane Tadcaster C288 0.5 days 06/05/17 06/05/17
A659 Tadcaster A659 1 day 07/05/17 07/05/17
Newton Kyme village Newton Kyme   0.5 days 08/05/17 08/05/17
Coulton Lane Appleton Roebuck C290 1.5 days 08/05/17 09/05/17